Question: 

We are finding it difficult to design permanent diagonal bracing for scissors trusses. The truss is often only a few feet in depth, which does not provide adequate room for diagonal bracing. Has SBCA come up with recommendations for permanent bracing of scissors trusses?

Question: 

Is it common practice for the supplier/distributor of a truss to provide a publication regarding temporary bracing with the delivery of the material?

Question: 

Manufactured gable ends are actually frames even though they are often referred to as trusses. The webs are “studs” oriented vertically and usually spaced at 12, 16 or 24 in. O.C. The gable end frame is designed to transfer vertical loads from the roof to the continuous bearing wall below. Another way gable end frames are different from trusses placed in the interior of the structure is that frames experience perpendicular wind loads. The sheathed frame transfers the wind loads to the roof and ceiling diaphragms and vice versa.

Question: 

I am a structural engineer designing pool cage structures that are typically attached to the house at the fascia board. Sometimes, the structure is attached where trusses are behind the fascia board and other times there is a framed gable end overhang. Do you know of any information concerning this additional load on the trusses or overhang under design wind loads? Is there a limiting distance on the amount of overhang? I know trusses are designed for certain uplift and the pool cage will add to this uplift at design load, but what about the gable end overhangs?

Question: 

Are there any schematics available on how to horizontally brace a 7/12 pitch roof?

Question: 

We have a local builder wishing to use floor trusses with a 2-hour assembly. I have shown him the 2-hour design on pages 17-27 of the second edition of SBCA’s Metal Plate Connected Wood Truss Handbook. Is this assembly UL approved? If so, what is the design number?

Question: 

In a small scale multi-family residential project, I'd like to use a wood truss floor-ceiling assembly to achieve a one hour separation between units. I'd like to directly attach the drywall to the underside of the trusses & use the truss space for ducts & lighting (the floor above will be lightweight concrete on plywood sub-floor). UL assemblies do not seem to address the duct/light penetrations in such an assembly. Can I achieve a one-hour rating in such an assembly and how are penetrations addressed? Can the ducts in the truss space serve both units above and below?

Question: 

Does the NFPA sprinkler standard address sprinkler loading? If so, how and where do I buy it? What other information do you have on sprinkler loading? How do other truss companies price jobs for sprinkler loading the plans do not include a sprinkler layout or even say what size/type of sprinkler system will be used?

Question: 

I have mono trusses on either side of a firewall. I have the fire rating/wall material between them. Can I place a ridge vent above these two? Or should I use vents? How do I calculate the appropriate vent sizes and styles?

Question: 

I have a 29 x 72 mobile office with a 2-foot deep wooden truss above the ceiling that a client is required to sprinkler. Is there any way to avoid sprinklering above the gypboard ceiling?