Question: 

What are the requirements on the permanent bracing of bottom chords? Can gypsum board diaphragms be used?

Question: 

I need to know how to repair a hole that has been drilled through a truss. In installing the wiring we improperly put the wires through the truss and now need to know the proper way to repair it.

Question: 

How often are trusses repaired?

Question: 

Is it common practice for the supplier/distributor of a truss to provide a publication regarding temporary bracing with the delivery of the material?

Question: 

In a small scale multi-family residential project, I'd like to use a wood truss floor-ceiling assembly to achieve a one hour separation between units. I'd like to directly attach the drywall to the underside of the trusses & use the truss space for ducts & lighting (the floor above will be lightweight concrete on plywood sub-floor). UL assemblies do not seem to address the duct/light penetrations in such an assembly. Can I achieve a one-hour rating in such an assembly and how are penetrations addressed? Can the ducts in the truss space serve both units above and below?

Question: 

Does the NFPA sprinkler standard address sprinkler loading? If so, how and where do I buy it? What other information do you have on sprinkler loading? How do other truss companies price jobs for sprinkler loading the plans do not include a sprinkler layout or even say what size/type of sprinkler system will be used?

Question: 

Are there any published studies or guidelines on the fire rating of floor trusses built with 2x3 lumber?

Question: 

The industry suggests notching the gable end truss to support the overhang. Is this wise? What about a structural gable, or a gable designed with drag loads, or one with only partial bearing? How safe is it for a framer working with a truss that has the top chord cut repeatedly?

Question: 

I am a building inspector and I have a question on information provided on truss design drawings. What does the uplift reaction number represent? Some manufacturers are very specific and state “to provide for mechanical connection of the truss to the top plate with a connector capable of withstanding a specific load.” Others simply list the uplift reaction with no further information. These are the ones that have caused a debate as to what the number actually represents.

Question: 

If trusses blew down from insufficient temporary bracing and the contractor put them back up without the knowledge of the truss manufacturer and gave the truss manufacturer a letter stating that the trusses were okay, is that sufficient? Do you know of any truss manufacturer who would accept this?