Design

Question: 

Our home has 2x4 roof trusses spanning 25 ft. spaced 16 in. O.C. Currently, there is limited attic storage on a plywood subfloor on the bottom chords, accessed via a small hatch in a closet. We would like to install a fold-down attic stair with a rough opening size of 25.5 in. x 54 in., with the long dimension perpendicular to the trusses. This would mean cutting the bottom chords of three trusses to frame the opening. Is this possible?

Question: 

My company supplied roof trusses for a hotel project. The building inspector shut the project down because the trusses were not designed to account for additional snowdrift loading. The construction plans did not contain any snowdrift loading information. The architect is claiming it is our responsibility to determine drift loading, therefore we must fix the problem. Do you have any documentation to help us dispute the architect’s claim?

Question: 

We are planning to add 1/2 in. cement board and 3/8 in. quarry tile to a kitchen floor. We need to know if the floor trusses will handle the additional weight. The floor trusses are 19.2 in. O.C. and the loading numbers are 40-10-0-5. What do these numbers mean?

Question: 

It is critical that permanent top chord bracing is supplied by proper nailing of the valley truss bottom chords to the carrying truss top chords, through purlins or properly installed rated roof sheathing. If the sheathing is not carried through under the valley framing, then the permanent top chord bracing must be supplied in another manner.

Question: 

Is the truss designer or the building designer responsible for calculating snow drift loads on a roof system?

Question: 

Would you please inform me of the specified requirements of the size and the amount of nail attachments from the truss to the top plate?

Question: 

Is it common practice for the supplier/distributor of a truss to provide a publication regarding temporary bracing with the delivery of the material?

Question: 

We are building churches in Europe. These are modified pole barns and we are trying to use local materials and local volunteer labor. Since the truss is the heart of the building, I am looking for a method to test some completed trusses before the building is started to make sure they are strong enough.

Question: 

I am a building inspector and I have a question on information provided on truss design drawings. What does the uplift reaction number represent? Some manufacturers are very specific and state “to provide for mechanical connection of the truss to the top plate with a connector capable of withstanding a specific load.” Others simply list the uplift reaction with no further information. These are the ones that have caused a debate as to what the number actually represents.

Question: 

The industry suggests notching the gable end truss to support the overhang. Is this wise? What about a structural gable, or a gable designed with drag loads, or one with only partial bearing? How safe is it for a framer working with a truss that has the top chord cut repeatedly?