Risk Management

Your company does it every day: load components and deliver them to jobsites. Ben Vadnais, assistant plant manager at Windsor Building Systems, has a few tips for keeping your loading and delivery operations running as smoothly and safely as possible.

Question: 

Is it the responsibility of the truss manufacturer to provide a sealed layout drawing for roof trusses?

Question: 

I have recently heard of a problem with fire-retardant-treated wood (FRTW) trusses that were manufactured and installed in 1965-1980. I was searching for more information, since my job involves the protection of property in our member school districts. I had heard that the trusses make of FRTW during that time period can or will become corrosive to the hardware and the trusses will fail.

Question: 

Is a Class A fire rating (provided by our liquid spray-on fire retardant) acceptable in certain situations?

Question: 

We have a customer that bought trusses in June. The trusses were shipped [ and one month later are] being set. The chords have weathered and bowed. What is the industry standard for dealing with this problem? What is our liability in this situation? We were not aware of any delays on the customer’s part and shipped as requested. Note: These trusses are 62 ft. scissor trusses.

Question: 

If trusses blew down from insufficient temporary bracing and the contractor put them back up without the knowledge of the truss manufacturer and gave the truss manufacturer a letter stating that the trusses were okay, is that sufficient? Do you know of any truss manufacturer who would accept this?

Question: 

Are wood trusses designed to be fall protection anchors that would support a worker should he fall?

Question: 

We have been specifying laminated veneer lumber (LVL) beams for some time now. The plans usually state, “Beam to be engineered and supplied by truss manufacturer.” What kind of liability issues do I need to watch out for?

Question: 

Consider this statement from a set of construction contract documents: “The Truss Manufacturer is responsible for inspecting the truss installation, bracing, anchorage and bearings and preparing a letter of verification stating that trusses are installed and braced properly.” At first glance, it may seem that the truss manufacturer is the most logical party to perform such an inspection. They are the truss experts, are they not?

Question: 

What is the industry standard for ordering residential roof truss systems: Should the general contractor/builder field measure before ordering trusses or should he rely on the blueprint? Who is responsible for their accuracy – the plan service, the truss manufacturer, the builder/general contractor or the framing contractor?