Jobsite Packages

Question: 

Some building designers believe that gable end webs need to be L-braced to 90% of the web length, which sounds fine. However, they spec that scissors gable end webs need to be braced to 100% of the web length. That means that in the field they are notching the braces to fit around top and bottom chords – you can imagine how difficult that can be. Is that necessary or even the intent of the web L-bracing?

Question: 

If trusses blew down from insufficient temporary bracing and the contractor put them back up without the knowledge of the truss manufacturer and gave the truss manufacturer a letter stating that the trusses were okay, is that sufficient? Do you know of any truss manufacturer who would accept this?

Question: 

How much OSB can be stacked on a floor deck without damaging the trusses?

Question: 

I almost always see wood trusses erected with no stability bracing at points of support. It seems to me that common sense and section 3.3.3.4 of The American Wood Council’s National Design Specification for Wood Construction (NDS) require that lateral support be provided at points of bearing. Plywood decking doesn't provide any more restraint for a wood truss than it does for a roof joist. I doubt if it was a concern with short span trusses having 4 in.

Question: 

We are finding it difficult to design permanent diagonal bracing for scissors trusses. The truss is often only a few feet in depth, which does not provide adequate room for diagonal bracing. Has SBCA come up with recommendations for permanent bracing of scissors trusses?

Question: 

We have been specifying laminated veneer lumber (LVL) beams for some time now. The plans usually state, “Beam to be engineered and supplied by truss manufacturer.” What kind of liability issues do I need to watch out for?

Question: 

It is critical that permanent top chord bracing is supplied by proper nailing of the valley truss bottom chords to the carrying truss top chords, through purlins or properly installed rated roof sheathing. If the sheathing is not carried through under the valley framing, then the permanent top chord bracing must be supplied in another manner.

This presentation provides information on truss submittal packages.

In order to promote the safe installation of building components including trusses, manufacturers send out a Jobsite Package to the construction site with the truss delivery. These Jobsite Packages include the Truss Submittal Package. The Truss Submittal Package includes the information that if required will be submitted to the Contractor/Building Designer, who if required will submit it to the local building official.

Woodhaven designed and built the roof and floor trusses for the Spruce Street Shul. Woodhaven also supplied the lumber and hardware for the project.